Vapour barrier, steel and formwork, checked in the last hours before any of it becomes concrete.
The vapour barrier is where slabs in this corridor go wrong: not extended beneath the whole slab, and punctures left unsealed. Neither can be corrected once the pour happens.

Annotated findings from Slab pre-pour inspections on Rockbank builds. Client addresses withheld.




1Bored piersAfter boring and cage placement, before concrete
3FrameOnce frame and trusses are up and the roof is on, before sarking
4Lock-up (pre-plaster)After roof, cladding and external doors, before plaster
5FixingAfter mouldings, doors and joinery, before painting
6WaterproofingAfter the membrane is applied and cured, before tiling
7Pre-handover (PCI)About a week before practical completionInstant online pricing, or talk to the booking team on 1300 471 805.
Because the barrier only works as a continuous layer. An unsealed puncture is a direct path for ground moisture, and it is invisible the moment concrete covers it.
Additional reinforcement the engineering requires where a rib spans beyond the prescribed limit. Missing them changes how that rib carries load.
A day out is normally enough, but let us know the moment a pour date is set.
That sits between you and your builder to resolve. Most items here are an hour's work.
AS 2870 with the engineering for your lot.
No. Concrete is final.